  • Last month, the Thirty Meter Telescope successfully completed the Test Results Review of the Telescope Tertiary Mirror (M3) Prototype. Chinese Academy of Sciences’ Changchun Institute of Optics, Fine Mechanics and Physics (CIOMP) engineers presented a series of tests on the M3 prototype, which received full approval from the members of the multinational review panel. As a result, CIOMP is now moving into the construction phase of its full-scale tertiary mirror system for TMT.

    M3 system, also called the Giant Steerable Science Mirror (GSSM), includes a 3.5m by 2.5m flat elliptical mirror, plus the mirror support system and the rigid body positioner that rotates and tilts the mirror so it can track with the telescope. The GSSM, located in the center of the primary mirror, is used to fold and steer the light path coming down from the secondary mirror, so the science beam can be delivered to any of the instruments active on the telescope.

    GSSM must be able to switch among the various science instruments rapidly and precisely, and keep the beam aligned with the instrument as the telescope changes its elevation angle.

    The scope of the M3 prototype review included the assembly of the prototype, the assembly steps and the testing realized in laboratory. Among the series of tests conducted were mounted and unmounted mirror surface figures, mass and center of gravity, vibration and resonant frequency, axis alignment, calibration, motion, bonding and finally the mirror cell support accuracy.

    For the past three years, CIOMP, selected by the TMT project office and by the National Astronomical Observatories of the Chinese Academy of Sciences (NAOC) to supply GSSM, has been designing, fabricating parts, procuring components, assembling and testing the prototype. Many of the tests are similar to the tests that will be done to evaluate the performances of the real-size GSSM for TMT.

    “CIOMP has worked very hard and has produced a nice piece of hardware,” said Virginia Ford, TMT M3 Work Package Manager. “As a precursor for the GSSM, the prototype hardware and its testing has helped the M3 team learn about this system and considerably reduce risks before construction. Most of the requirements have been successfully verified using the prototype, with only a few requirements left to complete verification during the upcoming design phase.”

    As a result of the review, the CIOMP team will proceed into the construction phase, where they will start the preliminary design phase for the real full-scale hardware production. Preliminary design, a period of analysis and computer-aided design (CAD) modeling is slated to kick off in March 2017.

    In the year to come, the mirror fabrication team will review the documentation to procure the M3 mirror blank and will proceed with their plans for fabricating the mirror. The precision mechanical team will perform a preliminary design of the entire GSSM. It is expected that the final GSSM design period, prior to start of fabrication, will take another 18 months. Panel Review members:

    Byron Smith (President, XDouble Dot, Manager, Discovery Channel Telescope) Chair Person,

    Tim Campbell (MF Campbell Consulting, formerly of Universal Antennas, Inc. and GD Satcom Technologies),

    Eric Hansen (TMT Optics Group Leader),

    Scott Shankle (TMT QA/QC Officer),

    Fengchuan Liu (TMT Deputy Project Manager),

    Glen Cole (TMT Optics Group, Optical Fabrication Engineer),

    Shen Zhixia (NAOC).

    Review Observers:

    Xue Suijian (Deputy Director-General of NAOC and Project Manager TMT China),

    Larry Stepp (TMT Telescope Leader),

    Scott Roberts (TMT Systems Engineering Group Leader),

    Bill Tyler (TMT ES&H/HRA/QA Officer),

    Myung Cho (Principal Opto-mechanical Engineer at National Optical Astronomy Observatory),

    Mark Sirota (TMT Controls Group Leader),

    Jimmy Johnson (TMT Controls Group, Software),

    John Roberts (TMT Systems Engineer),

    Jerry Nelson (TMT Project Scientist).

    CIOMP Presenters:

    Yang Fei, GSSM Prototype Assistant Manager

    Luo Xiao, Mirror Fabrication Lead

    Hu Haifei,

    Qi Erhui,

    Hu Haixiang,

    Guo Peng,

    Zhao Hongchao,

    An Qi-chang,

    Guo Pengfei.

    CIOMP Management Supporters

    Zhang Xuejun (Vice President of CIOMP, WP manager of GSSMP at CIOMP, and Director of Optical Fabrication),

    Zhang Liaming (Director of International Cooperation),

    Zhao Jinyu (Director of Precision Mechanics).

  • 原文来源:TMT’s Tertiary Mirror Enters Production Stage
相关报告
  • 《欧洲南方天文台签订合同制造极大望远镜(ELT)第三镜》

    • 来源专题:天文仪器与技术信息
    • 编译者:zwg@niaot.ac.cn
    • 发布时间:2017-02-23
    • ESO’s Extremely Large Telescope (ELT), scheduled to see first light in 2024, is at the cutting edge of telescope technology. Its optical system will consist of no fewer than five separate mirrors, each of them a significant engineering challenge. ESO has now awarded the contract to polish the third mirror in the light path, known as M3, to the French company Reosc [1], a subsidiary of Safran Electronics & Defense. They will receive the blank from SCHOTT, design the mirror and its mounting interfaces, polish the surface, and complete all necessary optical tests before delivery [2]. Reosc were also awarded the contracts to design, polish and test the telescope’s secondary mirror in July 2016, and to manufacture the deformable shell mirrors that will comprise the ELT’s fourth mirror (M4). M3 will be a giant 3.8-metre concave mirror — as big as the primary mirror of many of today’s world-class telescopes. It will be an unusual feature, as most current large telescopes such as ESO’s Very Large Telescope and the NASA/ESA Hubble Space Telescope use only two curved mirrors, sometimes using a flat tertiary mirror to redirect light to a convenient focus. The curved surface of M3 will work together with the primary and secondary mirrors to deliver a better image quality over a large field of view. The structural element of the mirror, before the reflective coating is applied, will be made of a sophisticated material called Zerodur™ from SCHOTT [3]. It will then need to be shaped and polished to a precision of 15 nanometres. Notes: [1] Reosc, a subsidiary of Sagem, a Safran high-technology company, is a world leader in the design, production and integration of high-performance optics, including for astronomy, space, high-energy lasers and the semiconductor industry. Reosc develops and produces high-performance optics for satellites, large telescopes and high-energy lasers, as well as the semiconductor industry. The company also built the single-piece 8-metre mirrors for ESO’s Very Large Telescope and the Gemini international telescopes, the 11-metre mirror for the Gran Telescopio de Canarias, mirrors for Europe’s Nirspec instrument on NASA’s James Webb Space Telescope, and mirrors for ESA’s GAIA astronomy satellite. [2] The contract to cast the M2 mirror blank was awarded on 18 January 2017. [3] Zerodur™ was originally developed for astronomical telescopes in the late 1960s. It has almost no thermal expansion even in the case of large temperature fluctuations, is highly chemically resistant, and can be polished to a high standard of finish. The actual reflective layer, made of aluminum or silver, is usually vapourised onto the extremely smooth surface shortly before the telescope is put into operation. Many well-known telescopes with Zerodur mirrors have been operating reliably for decades. They include, for example, ESO's Very Large Telescope in Chile.
  • 《美国三十米望远镜TMT红外成像光谱仪进入最后设计阶段》

    • 来源专题:天文仪器与技术信息
    • 编译者:zwg@niaot.ac.cn
    • 发布时间:2017-11-14
    • Following a successful second IRIS Preliminary Design Phase Review (PDR-2) at the TMT Project Office in Pasadena, IRIS is proceeding into its Final Design phase. The focus of the second review, held in September, involved an assessment of the IRIS software (including its data reduction system) and electrical design (including its detectors) as well as programmatic aspects spanning project cost and overall schedule. IRIS is a first light instrument designed to operate in the near-infrared (0.84-2.4 μm). It will enable the broad study of astronomical objects by providing data sets that are exquisite in their detail. It will achieve an angular resolution 10 times better than images from the Hubble Space Telescope. As one of the highest angular resolution near-infrared instruments in the world, it will help usher in a new era of astronomical study. The features of the design will enable a vast range of science goals covering numerous astrophysical domains including: solar system science, extrasolar planet studies, star formation processes, the physics super-massive black-holes and the composition and formation of galaxies, from our local neighborhood to high-redshift galaxies. Review participants included members of the IRIS team, external subject matter experts and key stakeholders. The review panel was chaired by Richard “Ric” Davies, senior scientist at Max-Planck Institute and the principal investigator of the Multi-AO Imaging Camera for Deep Observations (MICADO), one first light instrument for the E-ELT. In its initial feedback, the review board congratulated and acknowledged the IRIS team on the quality of the presentations and documentation delivered, recognizing the excellent work undertaken by the instrument team to complete the preliminary design phase. The review featured a thorough assessment of the readiness of the IRIS software design as well as the system’s electrical plan and a revisiting of its operational concepts. Additionally, the team presented its first quality assurance and safety plans. Lastly, PDR-2 also saw the team generate a cost proposal as well as produce its final design phase schedule. During the latter part of the preliminary design phase, the IRIS science team greatly expanded upon the instrument’s operational concepts, specifically addressing the steps and system interactions involved in preparing for and performing end-to-end observations. To this end, a thorough subset of the envisioned IRIS science cases walked through the anticipated software sequences. When delivered, IRIS will operate from 0.84 µm to 2.4 µm and offer diffraction-limited imaging and integral-field spectroscopy at wavelengths greater than 1 µm. The design will feature an Imager with a field-of-view of 34”x34” arcsec which relays light into the Integral Field Spectrograph (IFS). The IFS hosts two slicing techniques to sample the delivered field, each of these provides two plate scale options for a total of four modes. Of these, the lenslet channel will handle the finest plate scales; whereas, the slicer channel will provide coverage for the coarser ones. The IFS will support moderate spectral resolutions of R = 4,000. IRIS is being designed to take true advantage of all the gains afforded by a 30m class telescope. In its highest spatial sampling, the IFS will yield upwards of 14,000 individual simultaneous spectra. As one of TMT’s first-light instruments, IRIS needs to be versatile, and to this end, the observing modes are enriched by the instrument’s complement of 60 filters and 14 gratings. The IRIS collaborating institutions include The California Institute of Technology (CIT); The Nanjing Institute of Astronomical Optics and Technology (NIAOT); The National Astronomical Observatory of Japan (NAOJ); The National Research Council (NRC) of Canada Herzberg Astronomy & Astrophysics; The University of California at Los Angeles (UCLA); The University of California at San Diego (UCSD) and The University of California at Santa Cruz (UCSC).